Cement and sand for plaster – 12 mm and 20 mm

Quantities for cement plaster per 100 sq ft, using dry volume = wet volume × 1.33 (bulking and wastage).

wet volume = area × thickness · dry volume = wet × 1.33
cement (cum) = dry volume ÷ sum of ratio · 1 bag = 0.0347 cum

Per 100 sq ft (9.29 sq m)

PlasterCementSand
12 mm internal, 1:6≈ 0.6 bag≈ 4.5 cft
15 mm, 1:6≈ 0.75 bag≈ 5.6 cft
20 mm external, 1:4≈ 1.4 bags≈ 7 cft

Example: 1000 sq ft wall, 12 mm, 1:6

≈ 6 bags of cement and ≈ 45 cft of sand. Ceiling plaster is usually 6 mm in 1:3 (about 0.5 bag per 100 sq ft).